Contracted by Ross-Shire Engineering, Utile have designed, delivered, installed and commissioned a rapid air mixing package for United Utilities at Great Asby WwTW. With the order placed on September 2025 the final installation and completion was in February 2026. Designed and manufactured at their Northamptonshire facility, Utile developed a WIMES and UUplc Asset Standard compliant package to provide rapid air mixing to two tank chambers, one being for Coagulant dosing and the other Ferric Dosing. The efficiency of the Utile manufactured air compressors and mixing technology ensures very low running costs and highly effective sludge mixing in rapid time during operation. Each line is fitted with a variable area flow meter to provide a calibrated supply of air to match the dosing cycle.