Contracted by Tilbury Douglas Construction, Utile have delivered a turnkey air mixing package for Thames Water at Bourton-on-the-Water STW for a planned upgrade to suit the 2026/2031 design horizon. With Contract placement in May 2024, the installation in the new Thickened SAS Holding Tank was completed and bought on line in May 2026 after some unforeseen delays. Designed and manufactured at their Northamptonshire facility, Utile delivered a WIMES and TWUL Asset Standard compliant package to provide full and effective aerobic mixing within 1hr to the new Sludge holding tank before removal by tanker to a central treatment plant. The efficiency of the Utile manufactured air compressors and mixing technology enables it to handle variable sludge levels in the tank with the added benefit of preventing scum formation as well as aiding the reduction of Phosphates.